I have worked 29 years as Electrical Technician with voltage of 0,4 KV, 6 KV, 110 KV.

Work History

QA/QC - E&I Inspector


January 2013 - December 2013

•Period: January 2013 – December 2013
Position: QA/QC - E&I Inspector
Company & Location: Eni-Saipem- UAE Shah Gas Package 5
Responsibilities: QA/QC- supervision & Quality control during construction & Installation, responsible and familiarized with the job specifications, review all documentation associated with Electrical Installation , including Inspection &Test Plans(ITP), Procedures, Method Statements, Vendor Documentation , Maintenance &Operations Manuals and to survey the work of Subcontractor is done as per standards and specifications.
-Implementing coverage of proper installation, wiring and cable laying, cladding, termination, witnessing of insulation resistance test and hipot test.
-Coordinate and assist construction to resolve any encountered problems related to inspection and testing activities to meet schedule and avoid any delay of activities.
-Prepare internal punch list and coordinate with the construction prior for inspection.
-Coordinate with the client for punch list closure and final acceptance.
-Checking of single line diagram, engineering specification, material specification.
-Inspection of power lighting fixtures, earthing cables, earthing bus-bar, junction box, lightning protection system.
-Inspection of installation for pole lights, area lights, emergency and normal lights.
-Inspection and testing (insulation and continuity) of LV, Data and Fiber Optic cables.
-Inspection of CCTV system, Access control system, Optical and sound warning system.
-Test & draw out position, even incoming & Bus-tie circuit breakers shall be electrically interlocked.
-Participate in Walk Down for the completed system.

Electrical Technician

Tozzi Sud Spa-Ravenna Italy

August 2012 - November 2012

•Period: August 2012 – November 2012
Position: Electrical Technician
Company & Location: West Franklin project,Tozzi Sud -Ravenna
- Electrical connections in Technical Equipment Room.
- Connecting power cables in HVAC heaters panel.
- Connecting instrumentation cables in ABB-F&G marshaling cabinets.
- Connecting cables in field electrical and instrumentation JB.
- Electrical connections for local control stations.
- Connecting speakers for PA-GA systems.
- Connecting ESD push buttons.
- Pulling dressing and tagging cables .
- Installing Roxtec penetrations in panels and walls penetrations.
- Glanding cables with Hawke glands.

Electrical Supervisor & Electrical Technician

Techint Cimi_Montubi Nigeria Ltd

August 2010 - October 2011

•1 August 2010- 31 October 2011- CONSTRUCTION-GTL PROJECT (Gas to Liquid) - Electrical Supervisor & Electrical Technician - Electrical Construction:
I have worked in Nigeria, client Chevron- U.S.A. and Southern Gas Company Nigeria, contractor Techint Cimi_Montubi Nigeria Ltd as Electrical Technician &Electrical Supervisor specialist in the execution of electrical installations.
Here I have led 3 teams with 6-10 local workers each with which we have executed:
Team 1 worked - for cable trays; electrical circuits for normal lighting and emergency ; installing, connection and checking smoke detectors by stations and substation; erection and installing device for high mast lighting pole.
Team 2 worked :performed 3M joints for cable terminals ; Installing and connection batteries in battery room; installing infrared device for medium and high voltage panels; installing and connection junction box; installing, connection and checking electrical equipment's by station (panels, drawers, switches) ; different cables glands for the stations and substations.
Team 3 worked: Installing power transformers, installing Bus-duct ; connection bus bar inside of Bus-duct ;grounding; installing and connections for over 25 cathodic protection transformers ; realization of grid for cathodes protections around and inside the area; pulling cables.

QA/QC Electrical Inspector

Aker Solutions

January 2009 - October 2009

•ADRIATIC LNG project- AKER Solutions Italy platform-January-October 2009-QA/QC-E&I Inspector:
QA/QC- supervision & Quality control during construction & Installation, responsibility to Electrical Inspection for ITP(Inspection and Test Plan),
Single line diagram, engineering specification, material specification.
-All electrical component (cables, fuses, terminals, contactors, push buttons, relays, etc) must be clearly identified, and all component such as switchgear, protection relays, shall be marked with their main.
-Junction Boxes, earthing system, LV cables, cable ladder/trays, miscellaneous electrical equipment, switchgear mechanical interlocking ; integral facility of the switchgear to inhibit incorrect operation of the circuit breaker, padlock facilities for maintenance safety shall be provided with mechanical key interlock.
- Earthing connectors to incomers, bus bar & feeder circuits, interlock, lockable, bus-bar shutters shall be provided prevent incorrect or unsafe operation & prevent to access to live parts, & all withdrawble lock parts shall be lockable in the plug-in.
- Test & draw out position, even incoming & Bus-tie circuit breakers shall be electrically interlocked.
- Anti-vibration, fiber optic cables, performed/verified, installation and inspections as per P&ID, instrument data sheet & layout, schematic diagram.
-Inspection at:JB termination, cables schedule, function Test, pressure safety valves, UPS-System, Fire & Gas devices, fusible Plug loop Leak Test, Emergency Shut Down System.

Electrical Technician - Operating Gas Turbine-Turbo Mach


January 2007 - January 2009

•2007-2009-CHIMCOMPLEX S.A. BORZESTI :Electrical Technician - Operating Gas Turbine-Turbo Mach(day and night shift) - after upgrading work station processing 110KV/6KV-SRA1 CHIMCOMPLEX SA Borzesti, I was chosen to work electrical technician on a new plant to produce electricity(active energy-8MWh and reactive energy-4MVARh ) and steam(12 to 25 tones per hour) in the cogeneration system with gas turbine on TURBOMACHENERGYSYSTEMS(Switzerland) with turbine type Taurus T 70-CED-SOLONOX-CATERPILLAR SOLAR TURBINES U.S.A.
The whole process of producing electricity and steam , also the operating system that controls the startup of gas turbine and maneuvers performed with the electrical equipment of medium voltage 6 KV- Schneider Electrical and Merlin Gerrine Electrical is controlled by computer with operating program SCADA.
Here I work on shift- maintenance with new electrical equipment's:
-MV-Switchgears 17,5KV(MC-SET- Schneider).
-6KV-Withrawable circuit breakers(SF6-sulphurhexafluoride)-Merlin Gerrine.
-6KV-Withrawable circuit breakers(vacuum)-ABB.
-Sepam 40 control relays- Schneider.
-ABB REF 542 plus-control relays.
- Gas compressor 136 KW-Enerproject.
- 2 air compressors 7KW- Atlas Corps.
-Power Logic 800-Network analyzer - Merlin Gerrine.
-PLC- Siemens Simatic S7.
-Profibus nods- Beckhoff Automation AG.
-Power Flex 40 Static frequency converter for AC motors-Allen Bradley.
-Flex Pak 3000 Static converter for DC motors-Reliance Electric.
-UPS system:-PSS 18-110V and PSS 30-24 V for battery chargers.
-PSS 327-110V for Rectifier.

Electrical Technician- Power Transformer Stations 110KV/6KV


May 2000 - January 2007

•2000-2007-CHIMCOMPLEX S.A. BORZESTI :Electrical Technician- Operating High Voltage equipment's(day and night shift) - works of operating high voltage electrical equipment in an electrical power transformer station 110kv/6kv-SRA1 CHIMCOMPLEX S.A BORZESTI; perform maneuvers with electrical 110kv high voltage, power transformers 40MVA and 63MVA, switches 110KV with MOP devices (oleo-pneumatic mechanism), line separators on air 110kv power lines, related rigging equipment with electric medium voltage withdrawable circuits breakers 6KV on departures from sections bar, on electrical transformer station 110KV/6KV-SRA1 CHIMCOMPLEX S.A. BORZESTI.

Electrical Technician- Low Voltage Stations


May 1988 - May 2000

1988-2000-CHIMCOMPLEX S.A. BORZESTI :Electrical Technician- Operating Low Voltage equipment's (day and night shift) :

- within this period l have worked in many plants within this company such as : Soda M , Mercury electrolysis plant , day and night shifts ;
- my duty was to perform the following services :
-repairs , maintenance and operation of electrical motors of low and high voltage and HVAC equipment's.
- maintenance of roads lightning Inside and outside the company location.
- due to the fact that the operation of the company take place in a corrosive environment , I have also to replace the cable trays.
- I have performed erection and installation of switchboards for different types of electrical motors.
- I have worked in different plants with three – phase sockets and 220V sockets , switches, different types of lightning fixtures ,transformers and welding machines .
- being a chemical plant I’ve worked a lot in explosive medium with anti – ex equipment ,ventilation systems ,acoustic and optic warning devices for detection of gases within respective area.
- maintenance of low voltage stations and of main switchboards.
- I was involved in major overhauling on each of the plants , consisting on : checking the sealing of motors , bearings clearance , bearings greasing , push buttons force and triggering cables , painting motors.
-I have performed installation of switchboards for motors remote control with thermal relays, contactors, star-delta motor starters.



April 1985 - December 1986

•1985-1986: Romania-works of electrical maintenance and repairs on high-voltage(110 KV) equipment's in RAFO S.A.BORZESTI ,CAROM S.A.BORZESTI , CHIMCOMPLEX S.A. BORZESTI.

Qualifications & Certifications

Industrial High School-Electromechanical Instrumentation

Vocational Schoole-Electrical

Skillpages has been acquired by! is pioneering the way people find local services. Skillpages is the world’s premier directory of service providers.

Find out more

Mihai Anghel provides the following services:

Supported Countries
Choose your country