Kimchong - Steel Structure - Singapore

Lok Kimchong



Steel Structure


I have been working with one of top Steel Structure company in Singapore.
Currently post as Operations Manager in this company.

In-charge of Project in Oil & Gas, petrolchemical plant, Power Plant and etc.

Work History

SLNG Project (Samsung C&T)

t Meranti View Jurong Island- To supply, fabricated and erection of Pipe Rack Structure, Jetty Platform, Tank Platform and Building structure with total weight of 3800 tons to be completed by Mid 2012.

Operations Manager

January 2012 - July 2014

To in-charge all the project in Jurong Island, the project include;

1) SLNG Phase 2(Samsung C & T)-3000 tons
2) GMR Power Plant (Samsung C & T)-2500 tons
3) Lanxess PBR NdBR Phase 2( Foster Wheeler)-2000 tons
4) Nalco Project(Jacob''s)-1400 tons
5) Evonik(Jacob's)-7000 tons

Senior Project Manager

From January 2011

1) Lanxess BTR Project(Foster Wheeler) at 1 Tembusu Road Jurong Island-Supply, fabrication and erection of steel structure of Pipe rack structure, Process plant of Butyl Building, Halogenation Building and I-plant and also include of roofing, wall cladding and fire proofing work with total weight of 3500 tons to be completed by end 2011.

3-sorey Admin Building

JDC Coporation

August 2010 - July 2011

with Workshop, warehouse and Contractor office Facilities with total weight of 900 tons of steel.(2010 AUG-2011 JULY)

Tuas Power

April 2009 - December 2009

To supply, fabricated and erection of pipe rack on top of the existing Jetty and crossing of the existing canal by using barge crane. (2009 APR-2009 DEC)

Admin Office and ancillary facilities

Drill Quit Project(Lum Chang)

November 2009 - October 2010

To supply, fabricated and erection of a single-user industrial development with 1 block of 4-storey Admin Office and ancillary facilities. The steel structure work include cafeteria building, Pipe Storage, Coating building, Fabrication building, Finish Machine shop, warehouse and assembly building with total weight of 1900 tonnage.(2009 NOV-2010 OCT)

Power Seraya Plant Cogen

July 2008 - July 2009

Supply, fabrication and erection of 3700 tons of steel structure, including 2 unit of Turbine Generator Building, 3 KM pipe rack from Seraya Ave to Ayer Merbau road connect to PCS (Petrochemical Singapore) which involve of 65m long span, 45 tons in weight Pipe Bridge crossing the existing canal.(2008 JULY- 2009 JULY)

Project Manager

August 2007 - December 2010

Evonik Rohmax Singapore Plant

August 2007 - June 2008

at Sakra Ave Jurong Island-Supply, fabrication and erection of steel structure and Also include of roofing, wall cladding door, window and fire proofing work for the whole petrol and chemical plant 2007 AUG-2008 JUN

TTJ Design And Engineer

ing Pte Ltd

From January 2006

ing Pte Ltd/

Senior Project Engineer

January 2006 - October 2006

assist an ongoing project

Jurong Island Sakra Ave

January 2006 - March 2006

of supply, fabrication and erection of steel structure for Tate & Lyle sugar plant(from 2006 Jan to 2006 Mar)
2) Assigned to overseas project at The Kingtom of Bahrain (Middle East) which involve 3 major projects.
3) The Bahrain World Trade Central - To erect the tallest steel Twin Tower in Bahrain, the erection works carried out at the height of 186m from ground and the Twin Tower height is about 57m.
4) The Bahrain World Trade Central Turbine Bridge installation. The erection method is using the Hydraulic Strain Jack System to three different levels which is at level 10, level 26 and level 36.
5) The Alba (Aluminum Bahrain) Coke Shelter Plant - This involve of erection the maximum span of 94m at 42m height from ground roof trusses. The method of erection is by using two temporary supporting towers. Total tonnage: 1100 tons

Assistant Project Manager

November 2006 - July 2007

Abbott Nutrition Plant at Tuas South Ave 10/7(EPC Contractor Bovis lend Lease)Supply, fabrication and erection of 1800 tons of steel structure

• prepare and oversee implementation of project quality plan
• to ensure the projects are completed within the specified time schedule
• deploy resource viz. equipment / machinery and manpower to meet the project schedules and smooth running of project
• manage day to day operations of project
• attend principle meetings and other meetings with clients as necessary including safety-committee meetings
• monitoring major and critical material used for the project
• assist in the settlement of project final accounts


Up to December 2005

• 5 layer of temporary strut (including sheet piling & Kingpost installation) for Kallang-Paya Lebar Express Highway - Contract 422.
• This included the most critical part of project which needs to drive sheet pile under the existing MRT viaduct and the installation & dismantling of temporary strut. Also involve in the method statement submission

Assistant Project Manager

Eastpac Construction Pte Ltd

From July 2001

in-charge project as A & A to NTU 2 storey Sport & Recreation Center with contract value of S$3.5 million.

Site Engineer

Huah Siah Construction Pte Ltd

July 1999 - June 2001

• Pan Malaysia Cement at Tuas South Avenue 8-9, which is completed in-charge
• Erection of A 4-Storey logistic warehouse at Pioneer Sector 1 for PH Container Warehouse
• Erection of A 5-Storey logistic mega warehouse at Lot 721K Ayer Merbau Road, Jurong Island for M/S Poh Tiong Choon Logistic Ltd.

Site Engineer

Eng Tat Engineering Pte Ltd

April 1998 - July 1998

Site Engineer

Fuchi Engineering Pte Ltd

July 1998 - June 1999

• Road diversion decking at junction of Upper Serangoon Road and Potong Pasir Ave 1 for MRT NEL C705.
• Road diversion decking at junction of Upper Serangoon Road and Meyappa Chettiar Road for MRT NEL C705 Sennett Sation.
• 1 layer of temporary strut for MRT NEL C705 Boon Keng Station.
• 4 layers of horizontal strut and decking for Proposed Redevelopment of Old Hill Street Police Station at the junction of Hill Street and River Valley Road.
• 2 layers of horizontal strut and decking for Proposed Preservation and new erection to Lian Shan Shoung Lin Monastery (East Wing).

QC Engineer

Geahin Engineering Berhad, Malacca Malaysia

August 1997 - March 1998

Qualifications & Certifications