Batangan - Qs And Cost Estimate - Laoag City, Philippines

Leonel Batangan

Laoag City, Philippines


Every body describe that Filipino are "Hard working", But i says Filipino are "Patient Working".


Qs And Cost Estimate


Material and Quantity Take off for Civil and Electrical and Estimates Cost for Construction

Work History

Cost Engineer

First Balfour Inc

From November 2013

( QS/ Tracker for Overhead Transmission Line & Foundations)
Company: First Balfour Inc. ( Lopez Group of Company)
Project Assignment: 115KV Overhead Transmission line Burgos to Laoag S/S (NGCP)

Work Description
➢ Monitors Site Daily accomplishments for the foundation, tower erection & stringing.
➢ Prepares Weekly Progress accomplishments reports
➢ Monitors the daily Man-Hour of subcontractors for the purpose of data records.
➢ Monitors and evaluates the equipment usage of subcontractors for back charge purposes
➢ Check the material withdrawal of subcontractors for the purpose of controlling the excessive material withdrawal.
➢ Monitoring of Ready Mix Concrete and Job Mix Concrete for the cost related purposes.
➢ Evaluates subcontractors Bill of Quantity (BOQ) Accomplishments
➢ Checking some additional works at site for the purpose of claims specially for the hauling of materials in terms of distance.
➢ Estimates and evaluates at least Cost for the claims of subcontractors as possible.
➢ Checking and documentation for the Tower Defects at site installation for the purpose of records in case of demand cost repair of Tower to Tower Factory.
➢ Data tracking & recording for the start and finished of every foundations and towers for the data of planners use in works project schedule.

QS / COST Engineer for Electrical & Instruments


September 2011 - June 2013

(Advanced Technical Services and Construction)

Project Assignment: THPAL PROJECT (Taganito High Pressure Acid Leaching)
Barangay Taganito, Claver, Surigao Del Norte
Under the Management of TJCP (Taganito JGC Phil and Chyoda Project) Joint Venture
Work Description

➢ Daily monitoring, weekly and monthly progress accomplishments reported by subcontractors.
➢ Site Inspection/checking for the reported data accomplishments.
➢ Prepares report for Weekly Work Progress Accomplishments and Coordination with the Construction Managers in Electrical & Instruments and Site Manager for the work progress if accomplishments are at scheduled time.
➢ Prepares Monthly Progress Billing together with the required documents of the accomplished work for the month, as per required in the billing procedure of the Contract.
➢ Reconciles with the Main Contractor for the final approved quantity for payment.
➢ Prepares Change Notice Order to the Contractor if additional works is requested by contractor without any issuance of Site Instruction.
➢ Estimates Man-Hour, Material and Cost for the additional works (Site Instruction) request by the Contractor and check if project schedule does effect.
➢ Claims additional work (Site Instruction) to Main Contractor if ever the work is out of the contract.
➢ Processes claims for insurances incase for incidental occurrences at site.
➢ Analyses the flow of project base on data gathered to minimized cost control
➢ Ensures and maintain awareness that all works are at original scope of work and within the Contract.
➢ Performing risk and value management for cost control to maintain the monthly budget cost for Operational Expense (OPEX) and Capital Expense (CAPEX).
➢ Issuance of Site Instruction to subcontractors for some additional work that is not in the contract or scope of work.
➢ Monthly Progress Report evaluation for subcontractors Bill of Quantity.
➢ Evaluates the additional claims of subcontractors if it is possible.
➢ Payment Costing for Monthly...

Electrical Design

Showa Aztec Co., Ltd

Work Description
➢ Digitized electrical plan based on owner's request.
➢ Digitized Standard electrical plan based on contract requirements.
➢ Analyses plan if equipments are properly located at proper position.
➢ Rechecked and revises electrical plan base on contract standard
➢ Layouting for the power and lighting plan at standard system installation
➢ Computation for the proper illumination and positioning of lighting at critical areas.


Electrical Supervisor / Electrical Plan & Design


November 2009 - August 2011

(Advanced Technical Services and Construction)

Project Assignment: IBIDEN PHILIPPINES, INC.
Scrubber System for Factory "D" Expansion
Step 1, Step 2 & Step 3
First Philippine Industrial Park
(Santa Anastacia, Sto. Tomas Batangas)
Work Description
➢ Responsible for Electrical Plan & Design such as load computation, sizing of cables, circuit protection, power and lighting layout run ways. (AutoCAD).
➢ Materials take off (MTO).
➢ Digitized (AutoCAD) the procedure of installation for the purposed of safety measurements.
➢ Organize daily work schedules and supervise the work of electrical personnel's.
➢ Supervise electricians for carrying out in maintaining the standard installation of the electrical system.
➢ Ensures that cables, wires, lighting, motors and other installed equipment render QA/QC inspection signed with the Client.
➢ Monitoring the project is at work schedule.
➢ Weekly reporting to the company for the work project progress.
➢ Digitized As-Built Drawings for electrical (AutoCAD).
➢ Project Commissioning and Handover documents.
Installation Of Additional Aircon At Building A & B
Carmelray Industrial Park 1, Canlubang Calamba Laguna

(Advanced Technical Services and Construction)
Work Description
➢ Electrical Plan & Design (AutoCAD).
➢ Material Take Off (MTO).
➢ Digitized the procedure of installation for the purposed of safety measurements.
➢ Supervises electrical installation at standard procedure.
➢ Direct Control System Termination (Control Cables & Sensors)
➢ Ensures that cables, wires, motors control valve, motorized valve other installed equipment render QA/QC inspection signed with the Client.
➢ Monitoring the project is at work schedule.
➢ Meeting and reporting to the client for the work progress accomplishments.
➢ Digitized As-Built Drawing for electrical (AutoCAD).
➢ Project Commissioning and Handover.

Project Assignment: SAUDI RABIGH PHASE...

Qualifications & Certifications

Bachelor of Science in Electrical Engineering

Institute of Integrated

Electrical Engineering

Mariano Marcos State University

Sarrat National High School

Bacsil South Elementary School

Skillpages has been acquired by! is pioneering the way people find local services. Skillpages is the world’s premier directory of service providers.

Find out more

Supported Countries
Choose your country