Keith’s multifarious construction skills accumulated over 37 years have gravitated him to the position of Construction Manager. He has exceptional people management and team building skills. Keith has been responsible for safety, quality, HR/IR, procurement and Commercial for both major and minor projects with experience in the marine, mining, petrochemical, mechanical, structural, and civil construction sectors. Keith also has a diverse and varied construction and design management experiences in the energy and resource sectors.

Services

Construction Manager

Work History

Construction Manager

Minerals & Industrial

February 2013 - July 2013

Construction Manager- John Holland Minerals & Industrial
Wiggins Island Coal Export Terminal (WICET $220M)
Construction of an onshore coal Inloading and Outloading Facility.
Development of Target program. Site establishment and
mobilisation. Construction Planning and execution of initial start-up
works. Development of Human Resource mobilisation plan to align to program(270 workforce & 75 staff) and identification, selection and processing of subcontractors, plant and equipment and stores.

Construction Support Manager- John Holland Minerals & 0419167559

Industrial -New Business and Estimating

Construction specialist role providing expertise in tendering and planning of new projects. Developing sound construction
methodologies for project delivery including specialist crane lifts,
logistics, detailed planning, crew allocation and industrial relations.

Plant and Equipment identification and selection.Falsework
identification and selection. Indirect cost analysis. Staff
Organisation chart and workforce selection advice. Tender program
development.
Construction Manager

Construction Manager

John Holland Energy & Resources

Devil Creek Development Project Onshore Gas Plant ($200M)
Construction of an onshore processing facility comprising gas treatment / dehydration, condensate liquid
stabilisation, storage and road load-out, gas compression, metering and incorporating significant volume of earthworks and civil construction.

Construction Manager

John Holland Marine

Abbot Point Coal Terminal X50 Project Shiploader 2 ($49M)
Supply, fabrication and erection of a new Shiploader for the Abbot Point Coal Terminal, Bowen. The new
Shiploader was assembled in Brisbane, commissioned and then transferred to Bowen utilising a Heavy Lift
Vessel. Management of construction methodology & modulation, procurement, transport and logistics.
Development of modulation plans.

Construction Manager

John Holland Minerals & Industrial

Rapid Growth Project 4, Newman Hub ($100M)
BHP Billiton Iron Ore
Working with the Project Manager to ensure successful delivery. Involved in all aspects of safety, quality,
environment, commercial, commissioning, HR/IR and procurement related to the project.

Construction Manager

John Holland Minerals & Industrial

Yarwun 2 Aluminium Refinery, Gladstone ($137M)
Rio Tinto
Second stage of aluminium refinery covering 10,000T of structural steel erection, 110km of pipe, 40km of insulation and 600 mechanical bulks.
Development of methodology / modulation, procurement and logistics strategy. Management of modulation
delivery method.

Area Manager-John Holland Marine

BBI - Dalrymple Bay Coal Terminal

7X Marine
DBCT Outloading System & Berth 4 ($280M)
A new offshore outloading conveyor along a widened jetty extending 3.8km over the ocean to a new fourth
berth and outloading system. Responsible for operations within a delegated zone.

Site Manager

RG Tanna Third Shiploader

Gladstone ($22M)
Central Queensland Ports Authority
Upgrade of the RG Tanna Coal Terminal with the supply, fabrication and installation of a third shiploader.
Responsible for the supervision of staff and workforce and subcontractors. Programmed and co-ordinated
works, procurement, logistics and modulation strategy.

Superintendent

Brisbane Water Enviro Alliance

Brisbane City Council ($110M)
Supervised staff and workforce and contractors for the brownfields site upgrade of three key wastewater
plants in Brisbane. Responsible of the co-ordination of major packages and procurement of plant and resources.

Superintendent

John Holland Minerals & Industrial

Comalco Alumina Refinery
Construction Manager

Comalco Aluminium Ltd ($107M)
Responsible for the supervision of the Modulation and Consolidation Yard which pre-assembled modules for shipping to site. The project was to build an alumina refinery using the Bayer process to produce 1.4
million tonnes per annum of alumina in designated modules in Brisbane and sea transfer to Gladstone.

Crane Co-ordinator

Transfield Maintenance and Services

Caltex Refinery Outage - Major Turnaround
Night shift crane co-ordinator.

Shutdown Manager

Transfield Maintenance and Services

QNI Maintenance Project, Townsville & Yabulu
Responsible for the supervision of eight staff and 30 workforce and subcontractors.

Site Manager

Transfield Construction

Development Cells Project, Boyne Smelter, Gladstone
Responsible for the supervision of 85 workforce and subcontractors. Also of procurement of plant and resources.

General Foreman

Transfield Construction

Queensland(Civil)
Brisbane Airport Rail Link ($113.5M)
The construction, testing and commissioning of the Brisbane Airport Rail Link (8.5km) between Brisbane
Airport and Toombul, an elevated passenger railway service. Supervision of ten staff, workforce and subcontractors. Also the procurement of plant and resources.

Superintendent Structural / Mechanical

Piping

Queensland
CMB Joint Venture Century Mine Project ($45M)
Construction of crushing, stockpiling, thickeners, tanks piping, grinding and flotation facilities at the
Pasminco Century Zinc Mine. Supervision of 25 staff, and 232 workforce and subcontractors.

Superintendent

Queensland

QCL Expansion - Clinker Plant Structural / Mechanical / Piping, Gladstone ($40M)
Supply and erection of structural steel and mechanical installation and commissioning of materials handling and clinker process equipment at the QCL Plant. Supervision of 6 staff, and 40 workforce and subcontractors. Also the procurement of plant and resources.

Superintendent

Queensland

Boyne Smelter Expansion ($5M)
Supply, fabricate and erect 1,000T of structural steelwork to Rodding Ship and Bath Plant.

Superintendent

NSW Civil

CGS Site Port Kembla
Allocation and co-ordination of subcontractors, civil, mechanical, cranes, scaffolding, QA, safety, stressing,
electrical and technical procedures welding. Ensured safety and co-ordination etc for subcontractors and labourers.

Foreman

Transfield Construction

Construction Manager

Transfield Construction - NSW
BHP No. 4 Blast Furnace Reline, Stock Bins
Supervision of welding, erection and placement of steel, mechanical, and scaffolding cranes. Supervised 85
workforce and subcontractors.

Qualifications & Certifications

Queensland

University of Technology

Skillpages has been acquired by Bark.com!

Bark.com is pioneering the way people find local services. Skillpages is the world’s premier directory of service providers.

Find out more

Are you sure that you want to leave?